Duba 5 Drilling

 

Client: Northern Region Mekorot
On the project: Drilling production to reinforce the water supply system in the Cabri area, which discharges the water to pressure area 82+ bar
Drilled in an existing yard of Duba 3 well. The design included the expansion of the yard, retaining walls, electrical structure, transformer surface, diesel generator, landscape restoration etc.
Drilling depth 712m, pump installation depth 150 m.
The project was successfully completed and operating.

 

 

 

 

 